a) Active Transport Strategy
The Institute of Sensible Transport has been engaged to develop an Active Transport Strategy for Burnie. Four of seven stages (inception, data review, stakeholder engagement round 1, and site assessment) have been completed, and work on the draft strategy is underway.
b) Futuna Avenue and West Park Grove Roundabout – Contract 2718
Construction of the project has begun. New kerb and channel, and footpath has been poured. Roundabout core and traffic islands will be constructed in the coming weeks. Road base material and asphalt sealing to be completed before Easter.
c) Oonah Road – Guide River Bridge Replacement – Contract 2717
Construction of precast units has begun at TasSpan’s facilities for the replacement bridge, with site mobilisation and road closure to commence on 31 March 2025 and carry through to early May 2025.
d) Netball Centre – Court Resurfacing – Contract 2715
Hardings have completed all civil aspects of this project and have demobilised from site. Temporary linemarking was undertaken by Blacktac on 2 April 2025 for the Burnie Netball Association Wendy Berry Carnival, with court resurfacing due to commence on 12 April 2025.
e) McKenna Park Renovations
Construction has finished. Upon handing over for occupancy, it was flagged that the existing fire hydrant was non-compliant. Hydrant relocation work is now finished, and the Occupancy Permit has been finalised. The next milestone report is due 2 July 2025.
f) Bitumen Surfacing Services 2024–2025 – Contract 2713
Roadways and Hardings have almost completed 90% of the civil works associated with their respective bitumen surfacing sites. Civil works include replacing damaged kerb and channel, footpath, driveway crossovers, kerb outfalls, and gully pits. Bellavista Road has been sealed, and some other rural sites have been patched and are ready to be sealed. Most urban sites are also ready for sealing. Sites have all been marked up.
g) Burnie Cultural Precinct – BAFC Redevelopment (Stage 2) – Contract 2711
The Atrium has progressed with Tas Oak veneer panels installed to all internal walls. The lift shaft and walkways have been tiled in bluestone, and work on the Atrium floor will commence as soon as access equipment is removed.
The Long Room is nearing completion, with floor treatment complete and skirting being installed. Amenities, including the parenting room, are complete. Display joinery and interpretation elements are yet to commence.
Internal demolition of the Art Gallery is complete, with new wall and columns framed and plastered.
Creative play and learning areas are generally complete, pending acoustic ceiling treatment and lighting fit-off. Remedial works to the roof and internal area of the Artcade are complete, and DigiGlass glazing incorporating artwork by Indigenous artists has been installed.
The northern extension to the Long Room and Art Gallery has commenced, with LG slab poured and reinforcement and formwork for columns complete.
The Civic Plaza redevelopment is underway, with the area southwest of the building—including the main stairs—close to completion. This area connects existing adjacent car parking with the new entry.
h) Bitumen Surfacing Services 2023–2024 – Contract 2705
Ocean View Lane is the last site remaining for this contract. Hardings have completed stormwater upgrades at the site, and Telstra has completed pit relocation works. Hardings will now complete sealing by the end of the second week of April 2025.
i) Mount Street/Three Mile Line Road Roundabout Construction – Contract 2703
TasNetworks are currently undertaking lighting design for the intersection. Works will be completed in the new financial year.
j) Burnie Cultural Precinct – BAFC Redevelopment (Stage 1) – Contract 2694
Seating arrived in early January 2025 and has been installed in the Town Hall balcony. Handrails have also been installed to improve comfort for patrons using the stairs. This contract has now reached final completion.
k) Coastal Pathway – Contract 2702
Construction of the pathway and erosion works is now complete, with the official opening held on 24 October 2024. Final works are being completed, with the project due for full completion by June 2025.
l) Burnie Gateway Project
Site works are now complete, and final reports will be submitted and completed by June 2025.
m) City Centre Urban Plan
The Draft Urban Plan was adopted by Council at the February 2025 meeting. The Urban Plan working group has been established, with a first meeting scheduled for April 2025.
n) Flood Recovery Projects
Oonah Road East: Works are now complete, and the road reopened in early January 2025.
Upper Natone Road – Horseshoe Bend: Road remains under traffic management with a 5T load limit. Final design for the new alignment requires land acquisition. Consultants are negotiating with affected property owners.
o) Metro Bus All-Access Upgrade
All locations under this program are now complete, with two new shelters installed at Three Mile Line Road and Mooreville Road.
p) Kerb Ramp Upgrade Program
The annual kerb ramp upgrade program is now complete.
q) Reserve Footpath Renewal
Approximately 350 metres of gravel footpath has been replaced at Romaine Reserve with a wider concrete path. The increased width provides safer space for cyclists and pedestrians to pass. One section remains, to be completed once adjacent bridge upgrades are finalised later this financial year.
r) Romaine Dam Outlet Valve
GHD was contracted to design the outlet valve replacement, waterproofing, chamber upgrades, and pipe relining. Poly Welding Solutions completed construction, including installation of a new butterfly valve and pits. Construction is now complete.
s) Flood Risk Reduction Program – Ellis Road
Construction on Ellis Road is now complete, featuring around 230 metres of new 300mm rock-pitched drains along both sides of the roadway.
t) Footpath Replacement Program
Hardings are delivering this year’s program. Works are underway on Burnell Street, followed by Hale Street. Mount Street works are planned for the Easter school holidays.
u) Footpath Network Gap Program
Construction is underway and expected to finish before Easter. East Cam Road site is complete; works are halfway through at Scarfe Street.