Futuna Ave and West Park Grove Roundabout
- Contractor nameHardings Group
- Completion Date23 April 2025
The intersection of Futuna Avenue and West Park Grove has been identified as a safety concern due to a history of near-misses, poor visibility, and difficult turning movements, particularly during peak traffic periods.
Works to construct the roundabout at Futuna Ave and West Park Grove will commence on 13 January 2025. Harding's Group will be the contractor undertaking the works.
Works are expected to be completed April 2025 weather depending (extended from the original completion date of mid March).
During the construction traffic control will be in place to lower speeds, and some delays may occur.
This project has received funding under the Australian Government Black Spot Program
Updates:
Monday 14 April 2025
Construction of the project has begun. New kerb and channel, and footpath has been poured. Roundabout core and traffic islands will be constructed in the coming weeks. Road base material and asphalt sealing to be completed.
Roundabout Construction Schedule:
- Monday, 14th April: Begin deep lift placement at West Park Grove/ Futuna intersection.
-
Tuesday, 15th April: Start construction of the roundabout.
-
Wednesday, 16th April: Concrete pour for the roundabout with 60mpa
- Thursday, 17th April: Asphalt installation around the roundabout to ensure safe navigation for vehicles.
Location
Futuna Ave and West Park Grove, Park Grove View Map and directions
-41.0528247,145.8908595
Futuna Ave and West Park Grove ,
Park Grove
Futuna Ave and West Park Grove ,
Park Grove
Futuna Ave and West Park Grove Roundabout