Hodgman Street Road Closed - Civil Works

Published on 18 February 2025

FOGO (4).png

Hodgman Street will be closed to the public from 18 February to late April whilst Contractors work on the water main and demolish and reconstruct a failed section of the retaining wall on the eastern side.

We understand that this may cause some inconvenience and appreciate your patience and cooperation during the closure.

Signage and traffic management measures will be in place to help guide you safely around the affected areas.


Project Updates

4 April 2025

Contractors have been completing the foundations of the retaining wall, getting ready for the placing of the mass blocs.

Screenshot 2025-04-26 010028.png

 

28 March 2025

Contractors have been busy demolishing and reconstructing a failed section of the retaining wall on the eastern side.

Screenshot 2025-04-26 010008.png

 

21 February 2025

Harding's contractors have begun work on the water main, and will continue with reconstructing the failed section of the retaining wall on the eastern side.

Screenshot 2025-04-26 010452.png

Hodgman st.png