Romaine Reserve - Bridge and boardwalk replacement

  • Completion Date20 December 2025
BCC Social tiles (1080 x 1350) (12).jpg
 
The new Romaine bridge will be made of steel, and coated in Pine Green. We have widened it to 3m after listening to community input regarding our Active Transport Strategy (round 1).

 

Construction started onsite Thursday 17 July, to begin building up the northern end of the track. This will allow crane access for the bridge installation. Once the track is ready, our building crew will take over. They will be removing the old piers and installing the new ones. A new 3m wide boardwalk will then connect the pathway to the new structure.

 

We kindly ask all reserve users to adhere to all signage during these works. 

Construction Updates:

14 November 2025

With the Romaine bridge now bolted down, the decking has begun. The team have been installing FRP decking. This decking is made from a composite material that is resistant to corrosion, rot, UV degradation, and moisture.

IMG_0714.JPEG

 

IMG_0715.JPEG

 

28 October 2025

The new steel Romaine bridge has been lowered into place onto the prepared piers. The civil crew will be back on site next week to conduct the approach prep (building up the rock and base material for the pathway). Once completed, the building team will complete the installation of the structural footing components, the handrails, and some minor concrete works on the northern end.

20251028_152336.jpg

 

20251028_152351.jpg

 

20251028_152556.jpg

 

15 September 2025

The two northern bridge piers are 3.5m in the ground and have been filled with concrete, ready for the steel bridge frames that are currently being fabricated by Steel Works. 

 

15 September.jpg

 

15 September 2.jpg

 

9 September 2025

Councils building and civil teams have been working together boring large pier holes for the bridges' steel frame foundations.
They've laid concrete pads at the bottom of each hole, providing a base for the reinforced steel frames to sit on.
The southern foundations are now done, with the northern foundations underway!

 

IMG_0095.jpeg

 

20 August 2025

The building team have been busy installing the steel reinforcing bars, boxing and pour concrete for the southern bridge abutment at the romaine bridge replacement, which got poured today. 

20 August.jpg

 

17 August 2025

Your building and maintenance team have started on their part of the bridge and boardwalk replacement project. They have excavated the southern footing and poured the base for the bridge support.

17 August.jpg


17 July 2025

Our civil crew are onsite building up the northern end of the track. This will allow crane access for the bridge installation. Once the track is ready, our building crew will take over. They will be removing the old piers and installing the new ones. 

  • Pre-start meeting with Building and Civil Crew.
  • Works commenced on site preparation (removing existing piers and track widening/levelling).
  • Shop drawings received for 

 


Plans

BCC Social tiles (1080 x 1350) (7).jpg

September 2024

A fallen tree destroyed the pedestrian bridge, due to the extent of the damage this will not be a quick and easy fix

BCC Social tiles (1080 x 1350) (11).jpg

Location

11 Amanda Ct, Romaine 7320  View Map and directions

Google Map